Project Information

Between 2002 and 2004, a series of building and renovation interventions on storm water and sewerage systems were carried out, providing final design and works supervision services.

2002/04

Morlupo (Rome), Anzio (Rome), Rome - Italy

disegno tecnico disegno tecnico
sewage works sewage works
strada strada
sewage works sewage works
sewage works sewage works

 

Between 2002 and 2004, a series of building and renovation interventions on storm water and sewerage systems were carried out, providing final design and works supervision services.

Particularly, they included:

– The final design for the sewerage system on the Provincial Road “Morlupo Valle”, intervening in the area between the lift station, that collects the waste water from the village of Monte Vario, and the raised purification plant.

– the first executive phase for the construction of the sewerage system in the area of Sacida-Cavallo Morto in Anzio (RM); the pipeline was influenced by the land altimetry, the connection level to the existing plant as well as by the necessity to limit the depth of the trench.

– the adaptation of the existing sewage, to channel storm waters into the main sewage system, and the verification of the storm water drainage system of the AGESCI Scout base in Bracciano (RM), as a consequence of a hydrogeological disruption.